Date

 

Time1 PM
Duration30 mts 
Location

Zoom

Zoom
Attendees
Project/ProgramSecurity Assessment remediation - SAR 
Project BoardITS PMO 
Log Time
OTL
Objective(s)
  • Implement SAR Remediations

Notes: 


Speaker DescriptionNotes
SAR SAR Remediations Status

Progress Since Last Month starting 04/01/2022:
-Complete-Publish RTO/RPO on Streaming PROD 3.0 as is
-Complete -Create object/ tasks for data flow inventory
-Reviewed the access to workgroups with HANA team. HANA team to review access for TTS developers in ODC committee
-Security Assessment Remediation Tasks are in progress
  A. Ensure developers can not connect directly to the iPaaS system without utilizing a jump box
  B. Review third-party remote access to ensure access is still required

Activities for Next Month ending 05/31/2022:
-Design processes to ensure that production data doesn't flow in non-prod environments
-Prepare a template for documenting dataflow inventory
-Kick off Setup Periodic reviews of user account groups and roles

Reference Link An ODC group (Committee that decides the access) presentation 