Date |
|
---|---|
Time | 10.00 am |
Duration | 60 mts |
Location | Zoom |
Zoom | |
Attendees | |
Project/Program | Security Assessment remediation - SAR |
Project Board | ITS PMO |
Log Time | |
OTL | |
Objective(s) |
|
Notes:
Speaker | Description | Notes |
---|---|---|
SAR | Review the remediations that are ready for Security review | RA-128 – we will create a ticket. Let’s discuss the scope on Wednesday and who should it be assigned to
RA-130 – It seems that it was tagged as outside the scope for iPaaS. This needs to be done at ITS level
RA-131 – This is “in progress”. SMT may accept this risk. Please see the document link (column M). We can discuss this on Wednesday.
https://collab.ucsd.edu/display/IPAAS/HANA+Get_AH+access+How-To RA-16 – Analysis ready for review RA-19 – Analysis ready for review RA-25 – Closed (Already implemented) Achraf Adenane to review and prioritize only risks that are scoped to iPaas (column I). If it needs to be done at ITS level, we need to track those separately in a different project. |
New Remediations |
|
Add Comment